Place: Estonia, Tallin
Total area: 120 m2
Year: 2021
Architect: Kurt Hegge
The Cypress Bay High School Renovations, Repairs and Additions project is a phased renovation, repair, and addition project on an occupied campus, designed to relieve overcrowding and to provide the necessary building improvements to safely operate the school. The project features significant campus wide renovations and repairs, such as safety/ security upgrades, weight room renovations, and HVAC and building envelope improvements. The scope of work includes building envelope improvements to Building 8, HVAC and systems improvements to Buildings 1 and 3, and safety and security improvements to Building 99. The scope also includes the relocation of parent drop-off loop and parking, relocation and building envelope improvements to Building 85, and a new three-story, 78,885 SF classroom addition to replace 61 portables.
SIZE: 88,951SF
CONSTRUCTION COST: $17.9MM
COMPLETION DATE: July 2018
CLIENT: Zyscovich Architects